A comprehensive guide for Brisbane businesses planning their next commercial fitout or refurbishment

Planning an office fitout can feel overwhelming, especially when you’re trying to balance business operations with construction timelines. Whether you’re expanding into a new Brisbane location or refreshing your current space, proper planning is crucial for a successful outcome that stays on time and within budget.

At Trade Project Services, we’ve guided countless Brisbane businesses through successful commercial fitouts and refurbishments. After years of experience managing projects across Southeast Queensland, we’ve developed this comprehensive planning framework to help you navigate the complexities of your next office transformation.

Phase 1: Initial Planning & Strategy (8-12 weeks before start)

Week 1-2: Define Your Vision

□ Establish project goals and objectives

  • What problems is this fitout solving?
  • How will success be measured?
  • What’s driving the change (growth, lease renewal, employee retention)?

□ Determine your budget range

  • Include 10-15% contingency for unexpected costs
  • Consider furniture, technology, and ongoing operational changes
  • Factor in temporary workspace costs if needed

□ Form your project team

  • Appoint an internal project champion
  • Identify key stakeholders for decision-making
  • Consider external project management if needed.

 

Week 3-4: Space Requirements Analysis

□ Conduct a workplace audit

  • Current vs future headcount projections
  • Department-specific space needs
  • Meeting room and collaboration requirements
  • Storage and specialised equipment needs

□ Research Brisbane zoning and compliance requirements

  • Building Code of Australia (BCA) compliance
  • Disability Discrimination Act (DDA) requirements
  • Local council regulations
  • Fire safety and emergency egress requirements

□ Assess existing infrastructure

  • Current electrical capacity and distribution
  • Air conditioning zones and performance
  • Data cabling and telecommunications infrastructure
  • Structural limitations and opportunities.

 

Phase 2: Design & Documentation (6-10 weeks)

Week 5-6: Select Your Design Team

□ Interview fitout specialists

  • Review portfolios of Brisbane commercial projects
  • Check references and certifications
  • Understand their design process and timeline
  • Confirm insurance and licensing

□ Brief your chosen design team

  • Share your vision, budget, and timeline
  • Provide detailed space requirements
  • Discuss brand guidelines and aesthetic preferences

Week 7-10: Design Development

□ Review concept designs

  • Space planning and flow optimisation
  • Meeting room and breakout area placement
  • Reception and client-facing areas
  • Kitchen and amenity locations
  • Accessibility compliance throughout

□ Approve detailed designs

  • Furniture specifications and layouts
  • Lighting design and electrical requirements
  • Technology and AV integration
  • Finishes, colours, and materials selection
  • Signage and wayfinding systems

□ Obtain necessary approvals

  • Building permits (if required)
  • Strata approval for major works
  • Council development applications (if needed)
  • Fire safety compliance certification

□ Finalise material selections

  • Carpet and flooring specifications
  • Paint colours and wall finishes
  • Window treatments and privacy solutions
  • Sustainable and environmentally friendly options

Phase 3: Pre-Construction (4-6 weeks)

Week 11-12: Contractor Selection

□ Obtain detailed quotes

  • Request minimum 3 competitive quotes
  • Ensure all quotes cover the same scope
  • Verify contractor licensing and insurance
  • Check recent Brisbane project references

□ Review contracts thoroughly

  • Timeline and milestone payments
  • Variation management processes
  • Warranty and defect liability periods
  • Insurance and liability coverage

Week 13-16: Project Preparation and Mobilisation

□ Plan for business continuity

  • Arrange temporary workspace if needed
  • Communicate timeline to staff and clients
  • Plan IT infrastructure changes and data migration
  • Schedule furniture delivery and installation
  • Develop staff communication strategy

□ Coordinate with building management

  • Book service elevators for deliveries
  • Arrange after-hours access if required
  • Notify neighbouring tenants of potential disruption
  • Confirm parking arrangements for contractors and deliveries
  • Review building security and access protocols

□ Finalise contractor preparations

  • Confirm start date and key milestones
  • Review safety procedures and site induction requirements
  • Arrange site establishment and temporary facilities
  • Confirm material delivery schedules
  • Set up project communication systems

Phase 4: Construction Phase (4-12 weeks)

Week 17+: Active Construction

□ Weekly progress meetings

  • Review completed work against timeline
  • Address any issues or variations promptly
  • Confirm upcoming week’s activities
  • Manage any building management requirements
  • Monitor budget and approve any necessary changes

□ Quality control checkpoints

  • Regular site inspections with detailed documentation
  • Photo documentation of progress at key stages
  • Testing of electrical and data installations
  • Verification of compliance with approved designs
  • Early identification and resolution of defects

□ Prepare for handover

  • Schedule furniture delivery and coordination
  • Plan IT equipment installation and testing
  • Arrange professional cleaning and final touches
  • Coordinate staff move-in logistics and timing
  • Prepare handover documentation and warranties

□ Ongoing stakeholder management

  • Regular updates to senior management
  • Communication with affected staff members
  • Coordination with building management on disruptions
  • Management of any client or visitor impacts.

 

Phase 5: Completion & Move-In (1-2 weeks)

Final Week: Handover Process

□ Conduct detailed inspection

  • Create punch list of any defects
  • Test all systems (lighting, air conditioning, technology)
  • Verify compliance certificates
  • Obtain warranty documentation

□ Manage the move

  • Coordinate furniture installation
  • Set up IT systems and testing
  • Brief staff on new space features
  • Address any immediate issues

□ Project closure

  • Final payment to contractors
  • File all warranties and documentation
  • Conduct team debrief for lessons learned
  • Plan any remaining touch-ups or adjustments.

 

Brisbane-Specific Considerations

Climate Factors

  • Specify appropriate air conditioning for Queensland’s humid subtropical climate
  • Consider natural light management for west-facing windows during intense afternoon sun
  • Plan for potential storm season disruptions to construction schedules
  • Account for higher humidity levels affecting material installation and curing times

Local Regulations and Standards

  • Brisbane City Council requirements for commercial fitouts and change of use applications
  • Queensland Work Health and Safety regulations and compliance
  • Heritage considerations for older buildings in Brisbane’s CBD and inner suburbs
  • Strata title implications for fitout works in commercial complexes

Practical Brisbane Tips

  • Peak construction period is typically March through November
  • Factor in potential delays during storm season (December through February)
  • Consider public transport accessibility when planning parking and delivery logistics
  • Account for Brisbane’s rapid growth affecting material supply chains

 

  • Key Success Factors

Communication is Critical

  • Establish regular update schedules for all stakeholders
  • Implement clear decision-making processes with defined approval authorities
  • Ensure prompt responses to contractor queries to avoid delays
  • Maintain transparent communication about budget and timeline changes

Plan for the Unexpected

  • Hidden structural issues commonly found in older Brisbane buildings
  • Supply chain delays for specialised items, particularly imported materials
  • Weather-related construction delays during Brisbane’s storm season
  • Unforeseen building compliance requirements during heritage building refurbishments

Think Long-Term

  • Design for future growth and workplace flexibility
  • Invest in quality systems and infrastructure that will endure
  • Consider ongoing maintenance requirements and lifecycle costs
  • Plan for technology upgrades and changing workplace trends

Sustainability Considerations

  • Incorporate energy-efficient lighting and HVAC systems
  • Select sustainable materials with low environmental impact
  • Plan for waste reduction during construction and operation
  • Consider green building certification opportunities.

 

Ready to start planning your Brisbane office fitout? Trade Project Services has successfully delivered numerous commercial projects across Brisbane and Southeast Queensland. Our experienced team understands the unique challenges of Brisbane’s commercial property market and regulatory environment.

From heritage buildings in the CBD to modern developments in Newstead and South Brisbane, we’ve helped businesses of all sizes create functional, inspiring workspaces that support their growth and success.

Next Steps:

  • Contact Trade Project Services for a complimentary consultation and project timeline tailored to your specific needs
  • Schedule a site assessment with our experienced project managers
  • View our portfolio of recent Brisbane commercial fitout and refurbishment projects
  • Download our detailed fitout planning checklist and budget calculator